The Budget page (sidebar: Planning > Budget) shows what was planned, what is closed and what has already been paid. Every expense has three amounts: the estimate, the actual cost and what has been paid so far.

A new event’s budget page asks for the big number first.

  1. Click Set a total budget.
  2. Enter the amount and click Save.

You can change it any time from More actions (⋯) > Edit total budget, or Edit the budget on the first summary card. To start with an expense instead, click Or add a first expense by hand.

  • Our budget: the total, with a bar of what is paid and committed and how much is “closed so far”.
  • Paid so far: and what share of the commitments that is.
  • Left to pay: and in how many payments.
  • Still free: the budget minus the actual costs. When costs go beyond the total, the card turns into Over budget.
  • Cost per guest: the actual costs divided by your guests.
  1. Click New expense, or click an existing row to edit it.
  2. Enter the Expense name and choose a Category.
  3. Under Amounts, fill in Estimated cost, Actual cost and Paid so far.
  4. Optionally set the Next payment date, the Vendor, Notes and a linked Task (with Open to jump to it).
  5. Click Save expense.

The Payment status follows the amounts, so you don’t set it by hand: Paid, Deposit paid, Awaiting payment, No vendor yet or Not closed yet. If the actual cost goes over the estimate, the dialog says by how much and what is left to pay.

If someone else changed the same expense while you were editing, the dialog loads their version and tells you, instead of overwriting it. Deleting an expense asks for confirmation first.

Expense breakdown groups expenses by category. Each group can be collapsed and shows a bar of actual cost against its budget. Each row shows the estimate, actual cost and amount paid, a status chip, the vendor and the next payment date. A row that runs over its estimate turns red. The row’s ⋯ menu has Edit and Delete. On a phone, each row becomes a card.

When expenses go over their estimates, a banner says how many, by how much in total, and which is the largest. Show overruns filters the table to just those rows, and Show all expenses brings the rest back.

Where the money goes and upcoming payments

Section titled “Where the money goes and upcoming payments”
  • Where the money goes: a ring by category, switchable between Actual and Estimate, with each category’s amount and share.
  • Upcoming payments: what is due by date (“In 12 days”, “6 days late” in red), plus how many payments don’t have a date yet.

The currency selector in the page header changes the event currency. When an exchange rate is available, a Convert Currency dialog offers Convert all amounts or Just change symbol. If no rate is available, the currency code changes and the amounts stay as they are. Budget and vendor figures refresh right after.

More actions (⋯) > Export to CSV downloads every line with its category, vendor, status, estimate, actual, paid, overrun and next payment.